Contract Management & Procurement Flashcards
7 cards from real CCC practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Contract Management & Procurement flashcards as text
Which term describes the process of verifying that a contractor has completed contract requirements before final payment is authorized?
Answer: Contract closeout
Contract closeout is the formal process of verifying all deliverables are complete, resolving claims, and releasing final payment to the contractor.
A cost controller discovers that a subcontractor's invoices consistently exceed budgeted amounts without approved change orders. The FIRST action should be to:
Answer: Review the subcontract terms and compare invoices to contract line items
Before escalating or taking action, the cost controller must compare invoices against contracted line items to determine whether overruns are legitimate or unauthorized.
In competitive bidding, a 'bid bond' serves to:
Answer: Guarantee that the winning bidder will enter into the contract at the bid price
A bid bond protects the project owner by ensuring the winning bidder will sign the contract at the submitted bid price, covering losses if they fail to do so.
What is the purpose of a 'liquidated damages' clause in a procurement contract?
Answer: To predetermine compensation the owner receives for contractor delays
Liquidated damages clauses specify a daily or weekly financial penalty for contractor-caused delays, compensating the owner for losses without requiring proof of actual damages.
Which procurement document formally communicates the project requirements to potential vendors before they submit proposals?
Answer: Statement of Work (SOW)
The Statement of Work defines the technical, schedule, and performance requirements that vendors must meet, forming the basis for accurate and comparable proposals.
A cost controller is reviewing a contract for 'allowable costs.' Under US federal contracting regulations, which cost is typically UNALLOWABLE?
Answer: Entertainment and lobbying expenses
Under FAR (Federal Acquisition Regulation), entertainment, lobbying, and advertising costs are unallowable and cannot be charged to a government contract.
During contract execution, the practice of 'contract compliance monitoring' most directly supports cost control by:
Answer: Ensuring contractors deliver agreed scope without unauthorized cost growth
Compliance monitoring tracks contractor performance against contract terms, preventing scope creep and unauthorized cost increases that inflate project budgets.