A contractor submits a Request for Equitable Adjustment (REA) after the government changes the contract scope. What is the contractor claiming?
-
A
The right to terminate the contract immediately
-
B
Compensation for increased costs or time caused by a government-directed change
-
C
A waiver of all future performance obligations
-
D
An exemption from audit requirements