A budget specialist notices that the materials price variance is $15,000 unfavorable. Which action is most appropriate first?
-
A
Immediately revise the entire budget
-
B
Investigate the cause, such as supplier price increases or purchasing inefficiencies
-
C
Dismiss the variance as immaterial
-
D
Transfer funds from a different budget line