CBS Compliance & Risk Assessment 2 — Questions and Answers
Question 1: A budget specialist discovers that a department has been consistently overriding approved budget limits without documentation. Which internal control failure does this BEST represent?
- Lack of segregation of duties
- Absence of authorization controls (Correct answer)
- Inadequate variance reporting
- Poor cash flow forecasting
Correct answer: Absence of authorization controls
Authorization controls require approvals before budget limits are exceeded; their absence allows unauthorized overrides.
Question 2: Under the Federal Anti-Deficiency Act, a U.S. federal agency that obligates funds in excess of its appropriation is subject to which consequence?
- Mandatory budget sequestration
- Civil and criminal penalties for responsible officials (Correct answer)
- Automatic continuing resolution
- Reallocation from contingency reserves
Correct answer: Civil and criminal penalties for responsible officials
The Anti-Deficiency Act imposes civil and criminal penalties on officials who obligate or expend funds beyond appropriated amounts.
Question 3: Which risk appetite concept defines the maximum level of risk an organization is willing to accept before action is required?
- Risk tolerance
- Risk threshold (Correct answer)
- Risk capacity
- Risk velocity
Correct answer: Risk threshold
Risk threshold is the specific point at which risk levels trigger mandatory management action, distinguishing it from broader tolerance ranges.
Question 4: A CBS professional is reviewing a capital project budget. Which compliance check is MOST critical before funds are committed?
- Confirming vendor credit ratings
- Verifying legislative or board authorization for the project (Correct answer)
- Calculating net present value
- Reviewing prior-year actuals for the department
Correct answer: Verifying legislative or board authorization for the project
Capital commitments typically require explicit authorization from legislative bodies or governing boards before funds can be legally obligated.
Question 5: In enterprise risk management, a 'heat map' is used primarily to:
- Track employee overtime against budget
- Visually prioritize risks by likelihood and impact (Correct answer)
- Map budget variances to cost centers
- Display cash flow projections over time
Correct answer: Visually prioritize risks by likelihood and impact
A risk heat map plots risks on a matrix of likelihood versus impact, helping prioritize which risks demand the most attention.
Question 6: Which budget compliance mechanism ensures that spending does not exceed periodic allotments even if the annual appropriation is sufficient?
- Encumbrance accounting
- Allotment controls (Correct answer)
- Budget transfer authority
- Object-code restrictions
Correct answer: Allotment controls
Allotment controls divide annual appropriations into periodic spending limits, preventing front-loading or premature exhaustion of funds.
Question 7: When assessing compliance risk in a grant-funded program, which document establishes the primary legal obligations a budget specialist must verify?
- The organization's strategic plan
- The grant agreement and applicable OMB circulars or Uniform Guidance (Correct answer)
- The prior-year audit management letter
- The department head's spending priorities memo
Correct answer: The grant agreement and applicable OMB circulars or Uniform Guidance
The grant agreement combined with OMB Uniform Guidance (2 CFR 200) sets the binding compliance requirements for federally funded programs.
A budget specialist discovers that a department has been consistently overriding approved budget limits without documentation.
Which internal control failure does this BEST represent?