A 'no-damages-for-delay' clause in a construction contract typically means:
-
A
The contractor cannot be assessed liquidated damages
-
B
The contractor's only remedy for owner-caused delays is a time extension, not additional money
-
C
Delay damages are limited to 5% of the contract sum
-
D
The owner waives all rights to claim delay damages