A budget analyst is reviewing a public-private partnership (P3) agreement. Which risk is MOST commonly transferred to the private partner in such arrangements?
-
A
Legislative appropriation risk
-
B
Construction cost overrun and schedule risk
-
C
Congressional oversight risk
-
D
Freedom of Information Act (FOIA) compliance risk