CAT Project and Client Management 3 — Questions and Answers
Question 1: A client complains that the boardroom audio system you installed sounds different than what was demonstrated in a showroom. The MOST likely cause and resolution path is:
- Replace all speakers at no charge
- Compare actual room acoustics to demo environment and tune the DSP accordingly (Correct answer)
- Tell the client all systems sound the same
- Recommend the client hire an independent acoustician
Correct answer: Compare actual room acoustics to demo environment and tune the DSP accordingly
Room acoustics significantly affect perceived audio quality; comparing environments and tuning the DSP to match the actual space resolves the discrepancy.
Question 2: When preparing a bid for a commercial AV project, which factor MOST directly affects the accuracy of your labor estimate?
- Equipment list price from the manufacturer
- Accurate site survey and clearly defined scope of work (Correct answer)
- Number of competing bids submitted
- Client's preferred payment schedule
Correct answer: Accurate site survey and clearly defined scope of work
An accurate site survey and well-defined scope allow realistic assessment of installation complexity, cable runs, and man-hours required.
Question 3: A general contractor asks you to begin AV rough-in before the conduit sleeves have been installed by the electrical subcontractor. You should:
- Begin work immediately to stay on schedule
- Coordinate with the EC to establish a shared milestone before starting rough-in (Correct answer)
- Report the GC to the building authority
- Pull all your crew off-site until everything is ready
Correct answer: Coordinate with the EC to establish a shared milestone before starting rough-in
Coordinating with the electrical subcontractor to establish shared milestones prevents rework and ensures proper conduit placement before AV rough-in begins.
Question 4: Which document should a CAT use to formally request clarification on an ambiguous specification from an AV consultant during the design phase?
- Punch list
- Request for Information (RFI) (Correct answer)
- Submittal package
- Notice of Intent
Correct answer: Request for Information (RFI)
An RFI is the standard formal document used to request clarification on unclear or conflicting project specifications from the design team.
Question 5: A project owner requests weekly status reports during a 6-month AV installation. These reports should PRIMARILY address:
- Technical specifications of installed equipment
- Schedule adherence, budget status, and open issues/risks (Correct answer)
- Crew personal performance reviews
- Manufacturer warranty card tracking
Correct answer: Schedule adherence, budget status, and open issues/risks
Status reports give project owners visibility into schedule adherence, budget performance, and any issues that may require decisions or resources.
Question 6: During final commissioning of a conference room system, you discover a DSP output channel is labeled incorrectly in the programming. The BEST action is to:
- Leave it as-is and note it verbally to the client
- Correct the label in the DSP program and update the as-built documentation (Correct answer)
- Create a workaround by rewiring the audio output
- Submit a change order to reprogram the DSP
Correct answer: Correct the label in the DSP program and update the as-built documentation
Correcting the label in the DSP program and updating as-built documentation ensures accurate records for future service and troubleshooting.
Question 7: A client's facilities manager requests a training session for end users on the new AV control system. Scheduling this BEFORE substantial completion ensures:
- The client accepts the system without punch list items
- Users can provide operational feedback that may affect final adjustments (Correct answer)
- Training costs are eliminated from the contract
- The integrator avoids warranty service calls
Correct answer: Users can provide operational feedback that may affect final adjustments
Pre-completion training allows end users to identify operational issues while the integrator's team is still on-site to make adjustments.
A client complains that the boardroom audio system you installed sounds different than what was demonstrated in a showroom.
The MOST likely cause and resolution path is: