Project and Client Management Flashcards

7 cards from real CAT practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project and Client Management flashcards as text
  1. A client changes the scope of an AV installation mid-project by adding 12 additional ceiling speakers. What is the FIRST step a CAT should take?

    Answer: Issue a formal change order documenting added cost and timeline impact

    A formal change order protects both parties by documenting scope changes, revised costs, and updated timelines before work begins.

  2. Which document establishes the agreed-upon deliverables, schedule, and payment terms for a commercial AV project?

    Answer: Contract/Statement of Work

    A contract or Statement of Work defines deliverables, schedule, and payment terms and is the binding agreement between client and contractor.

  3. During a site walkthrough for a new boardroom AV system, you discover the ceiling height is 2 feet lower than shown on the architect's drawings. What should you do?

    Answer: Submit an RFI to the architect to resolve the discrepancy

    An RFI formally documents discrepancies between drawings and field conditions so the design team can issue corrected documentation.

  4. A commercial AV project has a hard opening deadline for a hotel grand ballroom. Which scheduling tool is MOST useful for identifying tasks that cannot be delayed without pushing the completion date?

    Answer: Critical path method (CPM)

    The critical path method identifies the sequence of dependent tasks whose delay would directly extend the overall project duration.

  5. A client requests a system demonstration before final payment is released. This review is BEST described as:

    Answer: System acceptance testing (SAT)

    System acceptance testing (SAT) is a formal client verification that the installed system meets specified performance requirements before final payment.

  6. When budgeting a large commercial AV installation, a contingency percentage is typically added to cover:

    Answer: Unforeseen conditions and scope uncertainties

    Contingency funds are reserved for unforeseen conditions, design changes, or scope uncertainties that arise during construction.

  7. A subcontractor on your AV project consistently submits invoices late, causing delays in your billing cycle. The BEST corrective action is to:

    Answer: Add invoice submission deadlines to the subcontract agreement

    Formalizing invoice submission deadlines in the subcontract agreement creates enforceable terms that protect cash flow and billing timelines.

Project and Client Management Flashcards โ€” CAT Study Cards with Answers