When performing a FMEA (Failure Mode and Effects Analysis), what does the Risk Priority Number (RPN) represent?
-
A
The total cost of fixing all failures
-
B
Severity × Occurrence × Detectability
-
C
The number of test cases required per failure mode
-
D
Impact × Likelihood only