A project team discovers a critical defect two days before release. The defect affects only 2% of users in a non-critical workflow. Which risk response is MOST appropriate?
-
A
Cancel the release immediately
-
B
Accept the risk and release with a known issues note
-
C
Transfer the risk to the QA manager
-
D
Avoid the risk by removing the workflow entirely