CAPM Risk & Quality Management 3 — Questions and Answers
Question 1: During which risk management process are risk owners assigned and risk response plans developed?
- Identify Risks
- Perform Qualitative Risk Analysis
- Perform Quantitative Risk Analysis
- Plan Risk Responses (Correct answer)
Correct answer: Plan Risk Responses
Plan Risk Responses is where the team develops options and assigns risk owners to execute agreed-upon response strategies.
Question 2: A control chart shows data points consistently above the mean for eight consecutive measurements. This situation is called:
- Common cause variation
- Special cause variation
- A rule of seven violation (Correct answer)
- Upper control limit breach
Correct answer: A rule of seven violation
The rule of seven states that seven or more consecutive data points on the same side of the mean indicate a non-random pattern requiring investigation.
Question 3: Which of the following is an example of a positive risk response strategy?
- Transfer
- Mitigate
- Exploit (Correct answer)
- Avoid
Correct answer: Exploit
Exploit is a positive risk response used to ensure that an opportunity definitely occurs, such as assigning the best resources to capture it.
Question 4: A project sponsor asks the project manager to add extra features beyond the agreed scope to impress the customer. This practice is known as:
- Scope creep
- Progressive elaboration
- Gold plating (Correct answer)
- Fast tracking
Correct answer: Gold plating
Gold plating refers to adding extras beyond the agreed scope, which increases risk without providing approved value.
Question 5: Which input to the Identify Risks process provides information about project objectives, constraints, and assumptions?
- Risk register
- Project management plan (Correct answer)
- Risk report
- Issue log
Correct answer: Project management plan
The project management plan contains scope, schedule, cost, and quality baselines that reveal areas of uncertainty used to identify risks.
Question 6: A project team performs regular process audits to evaluate whether quality processes are being followed correctly. This is an example of:
- Quality control
- Quality assurance (Correct answer)
- Continuous monitoring
- Risk auditing
Correct answer: Quality assurance
Quality assurance evaluates whether quality processes and standards are being properly applied across the project.
Question 7: Residual risks are best described as risks that:
- Have been transferred to a third party
- Remain after risk responses have been implemented (Correct answer)
- Are identified during project closure
- Were accepted without any response
Correct answer: Remain after risk responses have been implemented
Residual risks are those that remain after planned risk responses have been applied and should be documented and monitored.
During which risk management process are risk owners assigned and risk response plans developed?