CAPM Risk & Quality Management 2 — Questions and Answers
Question 1: Which risk response strategy involves shifting the negative impact of a risk to a third party?
- Avoid
- Mitigate
- Transfer (Correct answer)
- Accept
Correct answer: Transfer
Transfer moves the financial impact of a risk to a third party such as an insurance company or subcontractor.
Question 2: A project manager discovers that a supplier is consistently delivering components that fail quality inspections. Which quality tool is BEST for identifying the root cause?
- Control chart
- Pareto diagram
- Cause-and-effect diagram (Correct answer)
- Scatter diagram
Correct answer: Cause-and-effect diagram
A cause-and-effect (Ishikawa/fishbone) diagram helps teams systematically identify potential root causes of a defect.
Question 3: The probability of Risk A is 0.4 and its impact is $25,000. The probability of Risk B is 0.6 and its impact is $10,000. Which risk has the higher expected monetary value?
- Risk A at $10,000 (Correct answer)
- Risk B at $6,000
- Risk A at $25,000
- Both are equal at $10,000
Correct answer: Risk A at $10,000
EMV = Probability × Impact; Risk A = 0.4 × $25,000 = $10,000, Risk B = 0.6 × $10,000 = $6,000, so Risk A is higher.
Question 4: Which document formally authorizes the risk management activities and establishes the risk management approach for a project?
- Risk register
- Risk management plan (Correct answer)
- Project charter
- Issue log
Correct answer: Risk management plan
The risk management plan defines the methodology, roles, budget, and timing for risk management activities throughout the project.
Question 5: A project team reviews completed deliverables to confirm they meet defined requirements. This activity is an example of:
- Quality assurance
- Quality control (Correct answer)
- Risk monitoring
- Scope validation
Correct answer: Quality control
Quality control involves inspecting and measuring deliverables to verify they meet quality requirements.
Question 6: Which risk analysis technique uses a branching diagram to calculate the expected monetary value of various decision paths?
- Monte Carlo simulation
- Decision tree analysis (Correct answer)
- Sensitivity analysis
- SWOT analysis
Correct answer: Decision tree analysis
Decision tree analysis maps out possible outcomes of decisions along branches and uses EMV to evaluate the best path.
Question 7: A project manager wants to ensure defects are caught before the product reaches the customer at minimal cost. This best reflects which quality concept?
- Gold plating
- Cost of conformance (Correct answer)
- Cost of nonconformance
- Continuous improvement
Correct answer: Cost of conformance
Cost of conformance refers to money spent on prevention and appraisal activities to avoid failures, such as training and inspections.
Which risk response strategy involves shifting the negative impact of a risk to a third party?