A project manager is facing a resource conflict where two project activities require the same specialist at the same time. Which technique adjusts the schedule to work within resource constraints without extending the project end date?
-
A
Resource Leveling
-
B
Resource Smoothing
-
C
Crashing
-
D
Fast Tracking