CAPM Project Integration & Scope Management 5 — Questions and Answers
Question 1: When should the project manager develop the project management plan?
- After project execution begins
- Before the project charter is signed
- After the project charter is approved, during planning (Correct answer)
- Only after risks are fully identified
Correct answer: After the project charter is approved, during planning
The project management plan is developed during the Planning process group after the project has been formally authorized by the charter.
Question 2: Which scope management process ensures that only approved changes are incorporated into the revised scope baseline?
- Validate Scope
- Define Scope
- Control Scope (Correct answer)
- Create WBS
Correct answer: Control Scope
Control Scope monitors project and product scope status and manages changes to the scope baseline.
Question 3: A project manager notices that team members are doing extra work not in the WBS without any change request. This is an example of:
- Best practices in delivery
- Scope creep (Correct answer)
- Integrated change control
- Quality enhancement
Correct answer: Scope creep
Scope creep is the uncontrolled expansion of project scope without formal change control or adjustments to time and cost.
Question 4: What is the lowest level of the WBS called?
- Milestone
- Control Account
- Work Package (Correct answer)
- Activity
Correct answer: Work Package
Work packages are the lowest level of the WBS and represent deliverables that can be scheduled, cost estimated, monitored, and controlled.
Question 5: The integrated change control process requires that change requests be reviewed by:
- The project team only
- The change control board (CCB) (Correct answer)
- The project manager alone
- External auditors
Correct answer: The change control board (CCB)
The Change Control Board (CCB) is responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project.
Question 6: Which of the following is an input to the Develop Project Charter process?
- Project Management Plan
- Work Performance Reports
- Business Case (Correct answer)
- Lessons Learned Register
Correct answer: Business Case
The Business Case is a key input to Develop Project Charter as it provides the justification and financial analysis for the project.
Question 7: A project manager identifies that the project scope has expanded significantly due to unapproved changes. What corrective action is most appropriate?
- Accept the changes and update the WBS informally
- Stop the project immediately
- Submit retroactive change requests through integrated change control (Correct answer)
- Blame the team members responsible
Correct answer: Submit retroactive change requests through integrated change control
Retroactive change requests should be submitted through integrated change control to formally document and assess the scope changes.
When should the project manager develop the project management plan?