When comparing a predictive (waterfall) and an adaptive (agile) approach, integrated change control in adaptive projects is handled by:
-
A
A formal CCB that must approve all backlog changes
-
B
The product owner who manages and prioritizes the product backlog
-
C
The project sponsor who approves sprint scope changes
-
D
The PMO which controls all change requests