During the 'Close Project or Phase' process, which action ensures organizational learning is captured?
-
A
Releasing project resources back to functional managers
-
B
Archiving project documents and updating lessons learned
-
C
Obtaining formal acceptance of deliverables from the customer
-
D
Issuing the final project report to the sponsor