A project manager is managing a contract where the seller is paid $200,000 in costs plus a bonus if costs come in under the target. This describes which contract type?
-
A
Firm Fixed Price
-
B
Cost Plus Fixed Fee
-
C
Cost Plus Incentive Fee
-
D
Fixed Price Incentive Fee