CAPM Procurement & Contract Management 5 — Questions and Answers
Question 1: Which PMBOK process involves obtaining seller responses, selecting a seller, and awarding a contract?
- Plan Procurement Management
- Conduct Procurements (Correct answer)
- Control Procurements
- Close Procurements
Correct answer: Conduct Procurements
Conduct Procurements is the process of receiving seller bids, applying selection criteria, negotiating, and awarding the contract.
Question 2: What does 'Point of Total Assumption' (PTA) refer to in procurement?
- The moment a contract is officially signed by both parties
- The cost point in an FPIF contract above which the seller bears all cost overruns (Correct answer)
- The date when ownership of goods transfers from seller to buyer
- The budget threshold that triggers a contract renegotiation
Correct answer: The cost point in an FPIF contract above which the seller bears all cost overruns
The PTA in a Fixed Price Incentive Fee contract is the cost ceiling beyond which the seller assumes 100% of additional costs with no further fee.
Question 3: A Statement of Work (SOW) should be written in enough detail to allow sellers to:
- Determine the buyer's maximum budget
- Provide accurate pricing and understand what is required (Correct answer)
- Negotiate scope additions after contract award
- Assign their most junior resources to the work
Correct answer: Provide accurate pricing and understand what is required
A well-written SOW gives sellers sufficient clarity about deliverables, standards, and requirements to submit accurate and complete proposals.
Question 4: During contract negotiations, what is the purpose of establishing a 'Best Alternative to a Negotiated Agreement' (BATNA)?
- To identify the highest price the buyer is willing to pay
- To clarify your walk-away position if negotiations fail (Correct answer)
- To legally bind both parties to a preliminary agreement
- To document lessons learned from previous negotiations
Correct answer: To clarify your walk-away position if negotiations fail
BATNA defines the best outcome you can achieve if negotiations break down, strengthening your negotiating position and clarifying when to walk away.
Question 5: What is a 'Warranty' in the context of a procurement contract?
- A seller's guarantee of performance for a specified period after delivery (Correct answer)
- A clause that limits the buyer's right to inspect deliverables
- An agreement to extend the contract if additional work is needed
- A financial bond posted by the seller to ensure contract completion
Correct answer: A seller's guarantee of performance for a specified period after delivery
A warranty is a contractual commitment by the seller to repair or replace defective goods or services within a defined period after acceptance.
Question 6: Which of the following is an output of the Close Procurements process?
- Approved Change Requests
- Closed Procurements documentation and final payment (Correct answer)
- Procurement Statement of Work
- Qualified Sellers List
Correct answer: Closed Procurements documentation and final payment
Closed Procurements documentation, including final acceptance, formal closure notices, and records of lessons learned, are outputs of the Close Procurements process.
Question 7: When a buyer and seller cannot resolve a contract dispute through negotiation, the next preferred method per the PMBOK Guide is:
- Litigation in a court of law
- Mediation or Alternative Dispute Resolution (ADR) (Correct answer)
- Immediate contract termination
- Escalation to the project sponsor only
Correct answer: Mediation or Alternative Dispute Resolution (ADR)
The PMBOK Guide recommends Alternative Dispute Resolution (ADR) such as mediation or arbitration before resorting to costly litigation.
Which PMBOK process involves obtaining seller responses, selecting a seller, and awarding a contract?