CAPM Procurement & Contract Management 4 — Questions and Answers
Question 1: What is the purpose of a Procurement Management Plan?
- To document the qualifications of approved vendors
- To describe how procurement processes will be managed throughout the project (Correct answer)
- To list all contract clauses required by law
- To establish the project budget for purchased goods
Correct answer: To describe how procurement processes will be managed throughout the project
The Procurement Management Plan defines how procurement will be planned, executed, and controlled, including contract types and documentation requirements.
Question 2: Which contract clause protects the seller from liability due to events outside their control, such as natural disasters?
- Liquidated Damages Clause
- Force Majeure Clause (Correct answer)
- Indemnification Clause
- Warranty Clause
Correct answer: Force Majeure Clause
A Force Majeure clause excuses a party from performance obligations when extraordinary events beyond their control prevent fulfillment.
Question 3: During a procurement audit, the project manager notices the seller is billing hours for work not specified in the Statement of Work. This is best addressed through:
- Renegotiating the contract scope
- Raising a formal contract claim or dispute (Correct answer)
- Approving the additional hours to avoid conflict
- Amending the SOW to include the extra work
Correct answer: Raising a formal contract claim or dispute
Unauthorized billing that violates the contract terms should be formally disputed through the contract's claims and dispute resolution process.
Question 4: What is a 'Blanket Purchase Agreement' (BPA) used for?
- Purchasing one large, customized deliverable from a single seller
- Establishing pre-negotiated terms for repeated purchases of standard items (Correct answer)
- Ensuring all subcontractors are approved by the buyer
- Combining multiple contracts into a single master agreement
Correct answer: Establishing pre-negotiated terms for repeated purchases of standard items
A Blanket Purchase Agreement sets up pre-agreed pricing and terms for recurring purchases of routine goods or services, simplifying the ordering process.
Question 5: A seller submits a proposal that is significantly lower than all other bids. What concern should this raise for the project manager?
- The seller may be attempting bid rigging
- The seller may not fully understand the scope and could claim additional costs later (Correct answer)
- The buyer should immediately award the contract to this seller
- The other sellers should be asked to lower their prices
Correct answer: The seller may not fully understand the scope and could claim additional costs later
An unusually low bid may indicate the seller misunderstood scope, leading to claims, change orders, or inability to complete the work at that price.
Question 6: What is the role of a 'Contract Administrator' on a project?
- To write the original Request for Proposal
- To manage the day-to-day administration and performance of the contract (Correct answer)
- To select the winning vendor during source selection
- To conduct the procurement audit at project close
Correct answer: To manage the day-to-day administration and performance of the contract
The Contract Administrator oversees contract compliance, monitors seller performance, processes invoices, and manages changes during contract execution.
Question 7: In which situation would a Cost Plus Fixed Fee (CPFF) contract be most appropriate?
- When the scope is very well-defined and risks are low
- When the scope is uncertain and the seller's effort is difficult to predict (Correct answer)
- When the buyer wants to minimize administrative overhead
- When price competition between sellers is the primary goal
Correct answer: When the scope is uncertain and the seller's effort is difficult to predict
CPFF contracts are suited for research, development, or other projects with uncertain scope because the seller is reimbursed all allowable costs plus a fixed fee.
What is the purpose of a Procurement Management Plan?