A stakeholder asks why lessons learned sessions are held at phase gates rather than only at project close. The BEST response is:
-
A
Regulatory requirements mandate phase-gate reviews
-
B
Capturing lessons while events are fresh improves accuracy and allows in-project improvements
-
C
Phase-gate sessions fulfill the quality audit requirement
-
D
PMO policy requires phase-gate documentation