A project manager is told the project has CPI = 0.75 and SPI = 0.85. Which statement best describes the project status?
-
A
Over budget and ahead of schedule
-
B
Under budget and behind schedule
-
C
Over budget and behind schedule
-
D
Under budget and ahead of schedule