A project manager calculates VAC = −$15,000. What does this Variance at Completion indicate?
-
A
The project will finish $15,000 under budget
-
B
The project will finish $15,000 over budget
-
C
The project is $15,000 ahead of schedule
-
D
The project has $15,000 remaining in reserves