CAPM Practice Test
✕
📝 CAPM Practice Tests
Agile Frameworks
Agile & Hybrid Methodologies
Business Analysis
CAPM
Ethics & Professional Conduct
Project Closure & Benefits Realization
Change Control & Configuration
Communication & Stakeholder Management
Cost Management
Earned Value Management
Fundamentals & Core Concepts
Lessons Learned & Continuous Improvement
PMI Framework & Process Groups
Predictive Methodologies
Procurement & Contract Management
📖 CAPM Study Guides
CAPM Exam
CAPM Quick Exam
🎥 CAPM Videos
👑 CAPM VIP Certification Practice Exam
Flashcards
CAPM Flashcards
👑 CAPM VIP Flashcards
Study Guide
CAPM Study Guide
Cheat Sheet
CAPM Cheat Sheet
Articles
CAPM Canada: Complete Guide to Requirements, Eligibility, and Earning Your Certification
CAPM Certification 2026: Entry-Level Project Management Credential
CAPM Certification Jobs: Career Value & Salary Guide
CAPM Certification Requirements: Education, Eligibility, and Application Guide
CAPM Course Online: Best Training Options for Your Certification
CAPM Exam Prep: Project Management Certification Study Guide
CAPM Jobs and Career Overview: What You Can Do With the Certified Associate in Project Management
CAPM Practice Test 2026
CAPM Practice Test PDF (Free Printable 2026)
CAPM Practice Tests 2026 — Free Sample Questions for the Certified Associate in Project Management Exam
CAPM Pronunciation and What the Certification Really Means
CAPM Recertification: PDUs Required to Maintain Certification
CAPM Stands For: What It Is & Why It Matters
CAPM Study Materials: Complete Prep Guide for the PMI Certification
CAPM Training Programs: Top Courses, Boot Camps & Study Plans
Videos
CAPM Exam
☰
CAPM Practice Test
▶
CAPM Earned Value Management 2
Free · Instant Results
A project has a Budget at Completion (BAC) of $100,000 and is 60% complete. The Planned Value (PV) is $70,000 and the Actual Cost (AC) is $65,000. What is the Earned Value (EV)?
A
$60,000
B
$65,000
C
$70,000
D
$100,000