CAPM Cost Management 4 — Questions and Answers
Question 1: Which output of the Determine Budget process is used as the basis for measuring project cost performance?
- Project funding requirements
- Cost baseline (Correct answer)
- Cost management plan
- Activity cost estimates
Correct answer: Cost baseline
The cost baseline is the key output of Determine Budget and serves as the reference for measuring cost performance.
Question 2: A project has a TCPI of 1.15. What does this mean for the project team?
- The team must spend 15% more to complete the work
- The team must be 15% more efficient than planned to meet the BAC (Correct answer)
- The project is 15% under budget
- The project has a 15% schedule variance
Correct answer: The team must be 15% more efficient than planned to meet the BAC
TCPI > 1.0 means the team must work more efficiently than originally planned to finish within the authorized budget.
Question 3: When should a project manager escalate a cost variance issue through the formal change control process?
- For any cost variance, no matter how small
- When the variance exceeds established thresholds in the cost management plan (Correct answer)
- Only at project completion
- When the sponsor requests a status update
Correct answer: When the variance exceeds established thresholds in the cost management plan
The cost management plan defines thresholds for when variances require escalation through formal change control.
Question 4: Which cost estimating approach requires the most time and detail but typically provides the most accurate estimates?
- Analogous estimating
- Rough order of magnitude
- Bottom-up estimating (Correct answer)
- Parametric estimating
Correct answer: Bottom-up estimating
Bottom-up estimating aggregates estimates for individual work packages, requiring more effort but yielding the highest accuracy.
Question 5: A project's Planned Value at month 6 is $120,000, but the Earned Value is $90,000. What is the Schedule Variance?
- -$30,000 (Correct answer)
- +$30,000
- $120,000
- $90,000
Correct answer: -$30,000
SV = EV - PV = $90,000 - $120,000 = -$30,000, indicating the project is behind schedule.
Question 6: What is the primary difference between a cost estimate and a cost budget?
- Estimates are approved by sponsors; budgets are not
- A budget allocates costs over time and requires formal approval; an estimate does not (Correct answer)
- Estimates include contingency; budgets do not
- Budgets are created before estimates
Correct answer: A budget allocates costs over time and requires formal approval; an estimate does not
A cost budget allocates the cost estimates across the project timeline and requires formal approval to become the cost baseline.
Question 7: Which of the following is an example of a variable cost in a project?
- Equipment rental fee charged monthly
- One-time software license
- Contractor fees paid per deliverable completed (Correct answer)
- Fixed office space rental
Correct answer: Contractor fees paid per deliverable completed
Variable costs change based on usage or output, such as contractor fees tied to deliverables produced.
Which output of the Determine Budget process is used as the basis for measuring project cost performance?