A customer requests a 'small' wording change to a contractual deliverable. Why should this still go through formal change control?
-
A
Because all contract changes require legal approval
-
B
Because even small changes can affect scope, schedule, cost, or quality
-
C
Because the project charter requires it for all deliverables
-
D
Because only the CCB can define what is 'small'