A team member discovers that the project scope statement no longer reflects the agreed deliverables after several informal updates. What should the project manager do FIRST?
-
A
Rewrite the scope statement immediately
-
B
Submit a formal change request to update the scope baseline
-
C
Notify the customer that the scope has changed
-
D
Archive the old scope statement and proceed