Schedule Management Flashcards

7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Schedule Management flashcards as text
  1. What is total float (slack) in schedule management?

    Answer: The amount of time an activity can be delayed without delaying the project finish date

    Total float is the amount of time a scheduled activity can be delayed without delaying the project end date or violating a schedule constraint.

  2. Which type of dependency is inherent in the nature of the work and cannot be changed by the project team?

    Answer: Mandatory dependency

    Mandatory dependencies are inherent in the work being done (e.g., you must lay the foundation before building walls) and are also called hard logic.

  3. A project manager is applying schedule compression and finds that adding resources will not reduce duration further. What alternative compression technique could be used?

    Answer: Fast tracking

    Fast tracking overlaps activities that would normally be done sequentially, reducing duration without necessarily adding cost.

  4. Which tool is used to show schedule information against a calendar, displaying activity start and end dates as horizontal bars?

    Answer: Gantt chart

    A Gantt chart (bar chart) displays project activities against a calendar timeline as horizontal bars showing start and finish dates.

  5. What is free float in project scheduling?

    Answer: The time an activity can be delayed without delaying any successor activity

    Free float is the amount of time a scheduled activity can be delayed without delaying the early start of any immediately following scheduled activities.

  6. During schedule development, a project manager identifies that Activity B cannot start until Activity A is 50% complete. What type of relationship is this?

    Answer: Start-to-Start with lag

    A Start-to-Start relationship with lag means Activity B can start only after Activity A has been underway for a certain time (50% completion).

  7. Which process involves reviewing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule?

    Answer: Develop Schedule

    Develop Schedule analyzes activity sequences, durations, resource requirements, and constraints to create the schedule model.