  1. Which of the following describes the overall risk of a project rather than individual risks?

    Answer: Overall project risk

    Overall project risk represents the combined effect of all project uncertainties on the project outcome as a whole.

  2. A risk probability and impact matrix is used primarily to:

    Answer: Prioritize risks for further analysis

    The probability and impact matrix helps categorize and prioritize risks based on their likelihood and potential effect.

  3. Which of the following is an example of a risk mitigation strategy?

    Answer: Adding prototype testing to reduce technical uncertainty

    Mitigation reduces the probability or impact of a risk, and prototyping is a classic example of reducing technical uncertainty.

  4. Which technique involves gathering expert opinions anonymously to identify and assess risks?

    Answer: Delphi technique

    The Delphi technique uses multiple rounds of anonymous expert input to build consensus on risk identification and assessment.

  5. A project's risk threshold defines:

    Answer: The level of risk exposure above which action must be taken

    Risk thresholds are specific points at which a risk becomes unacceptable and must be addressed with a response.

  6. When performing Identify Risks, which of the following is an output?

    Answer: Risk register updates

    The risk register is created or updated as an output of the Identify Risks process, capturing all newly identified risks.

  7. A project manager notices that after implementing a risk response, the risk still has a residual probability of 10%. This remaining risk is called:

    Answer: Residual risk

    Residual risks are the risks that remain after risk responses have been implemented and should be monitored.