← All CAPM Flashcard Decks

Project Scope Management Flashcards

7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Scope Management flashcards as text
  1. During project execution, the customer requests adding a new feature. The project manager should FIRST:

    Answer: Process the request through the integrated change control process

    All change requests must be processed through integrated change control to evaluate impacts before approval or rejection.

  2. Which output of the Validate Scope process formally documents accepted deliverables?

    Answer: Accepted deliverables

    Accepted deliverables are the formally documented output when stakeholders or customers approve completed deliverables during Validate Scope.

  3. The 100% rule in WBS development means:

    Answer: The WBS must capture 100% of the project scope with no omissions or overlaps

    The 100% rule states the WBS must represent the entire project scope—no more and no less—to avoid gaps or duplication.

  4. Scope validation is primarily concerned with:

    Answer: Obtaining formal acceptance of completed deliverables

    Validate Scope focuses on obtaining formal stakeholder acceptance of completed project deliverables.

  5. A project manager wants to understand what stakeholders need from the project. Which document captures the conditions or capabilities a product must have to satisfy stakeholder needs?

    Answer: Requirements documentation

    Requirements documentation records the conditions, capabilities, and characteristics that must be met to satisfy stakeholder needs.

  6. Which of the following is NOT a technique used in the Collect Requirements process?

    Answer: Decomposition

    Decomposition is a technique used in the Create WBS process, not in Collect Requirements.

  7. The scope baseline consists of which THREE components?

    Answer: Project Scope Statement, WBS, and WBS Dictionary

    The scope baseline is made up of the approved Project Scope Statement, WBS, and WBS Dictionary.