Project Documentation & Reporting Flashcards
7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Project Documentation & Reporting flashcards as text
A stakeholder requests information that was not planned in the communications management plan. The project manager should FIRST:
Answer: Evaluate the request and update the communications management plan if warranted
The project manager should assess the new communication need and update the communications management plan to reflect any approved changes to reporting requirements.
A project assumption is BEST described as:
Answer: A factor considered true without proof for planning purposes
Assumptions are factors that are considered to be true, real, or certain without proof or demonstration for planning purposes.
Which report provides a forecast of future project performance based on current trends?
Answer: Trend report
A trend report examines project results over time to determine whether performance is improving or deteriorating, enabling forward-looking forecasts.
The configuration management plan is a component of the project management plan that addresses which concern?
Answer: How project deliverable versions are identified and controlled
The configuration management plan describes how information about project items will be documented, versions managed, and changes controlled.
During a weekly team meeting, the project manager reviews a document listing open issues, responsible owners, and target resolution dates. This document is BEST described as:
Answer: Issue log
An issue log records open problems and conflicts, who is responsible for resolving them, and the target dates for resolution.
A project manager wants to confirm that all project deliverables have been formally accepted before closing the project. Which document provides this evidence?
Answer: Accepted deliverables documentation
Accepted deliverables are documented outputs verified by the customer or sponsor, confirming that the deliverables meet the defined acceptance criteria.
Which element is typically NOT included in a project status report?
Answer: Stakeholder salary information
Status reports cover project performance information such as scope, schedule, and cost status, but do not include personal stakeholder data like salaries.