โ† All CAPM Flashcard Decks

Lessons Learned & Continuous Improvement Flashcards

7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Lessons Learned & Continuous Improvement flashcards as text
  1. A project manager facilitates a lessons learned session but team members are reluctant to share failures. What is the BEST facilitation approach?

    Answer: Create a blame-free environment focused on process improvement rather than individual fault

    A psychologically safe, blame-free environment encourages honest sharing of failures, which yields the most valuable lessons.

  2. Which statement about lessons learned is TRUE according to PMBOK?

    Answer: Lessons learned may be collected at any point during the project

    PMBOK states that lessons learned should be identified throughout the project lifecycle, not only at the end.

  3. A PDCA cycle (Plan-Do-Check-Act) is being used on a project. In which step would a team evaluate whether a process change achieved the desired improvement?

    Answer: Check

    The Check step involves evaluating results of the implemented change against expected outcomes to determine effectiveness.

  4. Which tool would BEST help a project team quantify the frequency of defect types identified in lessons learned to prioritize which issues to address first?

    Answer: Pareto chart

    A Pareto chart ranks defects by frequency, helping teams focus on the vital few issues that cause the most problems.

  5. A project manager is closing a project and must ensure lessons learned are accessible to future teams. Which action is MOST appropriate?

    Answer: Archive the lessons learned register in the organizational knowledge repository

    Storing lessons learned in the organizational knowledge repository ensures they are accessible to future project teams across the organization.

  6. A project manager applies a lesson from a past project to avoid a scheduling pitfall. Which PMBOK input category does this represent?

    Answer: Organizational process assets

    Lessons learned from previous projects are organizational process assets that inform planning and execution of current projects.

  7. A retrospective reveals that the team consistently underestimates testing duration. The BEST continuous improvement action is to:

    Answer: Update the estimating process to include a standard testing buffer informed by historical data

    Updating the estimating process using historical actuals is a data-driven continuous improvement action that prevents recurrence.