Earned Value Management Flashcards
7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Earned Value Management flashcards as text
A project manager is told the project has CPI = 0.75 and SPI = 0.85. Which statement best describes the project status?
Answer: Over budget and behind schedule
CPI < 1.0 means over budget; SPI < 1.0 means behind schedule — both metrics indicate unfavorable performance.
Which technique assigns EV credit only when a work package is 100% complete?
Answer: 0/100 method
The 0/100 method gives no earned value credit until the work package is fully completed.
The 50/50 earned value measurement method credits how much EV at the start of a work package?
Answer: 50%
The 50/50 rule gives 50% EV credit when the work package begins and the remaining 50% when it is completed.
Which EVM component is sometimes called 'Budgeted Cost of Work Scheduled' (BCWS)?
Answer: Planned Value (PV)
PV was historically called BCWS — it represents the authorized budget for scheduled work up to a given point.
A project's EAC is $120,000 and its BAC is $100,000. What is the VAC?
Answer: −$20,000
VAC = BAC − EAC = $100,000 − $120,000 = −$20,000, indicating a projected cost overrun of $20,000.
Which of the following is NOT a valid method for estimating EAC?
Answer: EV × SPI
Multiplying EV by SPI does not produce a valid EAC formula; the three standard approaches all start from AC.
During a project status meeting, the project manager reports EV = $50,000 and AC = $50,000. What can be concluded?
Answer: The project is exactly on budget
CV = EV − AC = $0 means the value earned exactly equals the money spent — the project is on budget at this point.