When a key stakeholder consistently misses scheduled update meetings, what is the most effective first response?
-
A
Escalate the issue to senior management immediately
-
B
Send a formal written warning about the missed meetings
-
C
Reach out directly to understand their preferred communication format and timing
-
D
Continue sending meeting invites and document non-attendance