CAM Risk Management 1 — Questions and Answers
Question 1: What is the primary purpose of risk management in aviation operations?
- To eliminate all hazards from the workplace
- To identify, assess, and mitigate hazards to an acceptable level (Correct answer)
- To transfer all operational risk to insurance providers
- To document incidents after they occur for regulatory reporting
Correct answer: To identify, assess, and mitigate hazards to an acceptable level
Risk management aims to identify and assess hazards and then implement controls to reduce risk to an acceptable level, not eliminate all hazards entirely.
Question 2: In a standard aviation risk matrix, which two factors are used to calculate a risk score?
- Cost and frequency
- Likelihood and severity (Correct answer)
- Duration and exposure
- Probability and complexity
Correct answer: Likelihood and severity
A risk matrix plots the likelihood (probability) of an occurrence against the severity (consequence) of its outcome to determine overall risk level.
Question 3: What does the term 'residual risk' refer to in aviation risk management?
- Risk that has been fully eliminated through controls
- Risk that remains after all mitigation measures have been applied (Correct answer)
- The initial risk level before any assessment is performed
- Risk transferred to a third party through insurance
Correct answer: Risk that remains after all mitigation measures have been applied
Residual risk is the level of risk that remains after controls and mitigation strategies have been implemented — it is the risk an organization accepts.
Question 4: Which ICAO document provides the global framework for Safety Management Systems (SMS) and risk management in aviation?
- Annex 6 — Operation of Aircraft
- Annex 19 — Safety Management (Correct answer)
- Annex 14 — Aerodromes
- Doc 9859 — Safety Management Manual
Correct answer: Annex 19 — Safety Management
ICAO Annex 19 is dedicated to Safety Management and contains the standards and recommended practices for implementing SMS, including risk management processes.
Question 5: A bowtie analysis in aviation risk management is best described as a tool that:
- Calculates the financial cost of a risk event
- Visualizes the causes of a hazard on one side and consequences on the other, with the event in the middle (Correct answer)
- Ranks hazards in order of regulatory priority
- Maps organizational reporting lines for safety officers
Correct answer: Visualizes the causes of a hazard on one side and consequences on the other, with the event in the middle
A bowtie diagram places the hazard/event in the center, showing threat pathways (causes) on the left and consequence pathways on the right, with barriers on both sides.
Question 6: In the context of the hierarchy of risk controls, which option is considered the most effective?
- Personal protective equipment (PPE)
- Administrative controls and procedures
- Engineering controls and elimination (Correct answer)
- Training and awareness programs
Correct answer: Engineering controls and elimination
Engineering controls and elimination sit at the top of the hierarchy because they physically remove or reduce the hazard rather than relying on human behavior.
Question 7: What is the correct sequence of steps in the basic aviation risk management process?
- Mitigate → Identify → Assess → Monitor
- Assess → Identify → Mitigate → Report
- Identify → Assess → Control → Monitor (Correct answer)
- Control → Assess → Identify → Accept
Correct answer: Identify → Assess → Control → Monitor
The standard risk management cycle is: Identify hazards, Assess the associated risk, implement Controls or mitigations, then Monitor effectiveness — commonly called IACM.
What is the primary purpose of risk management in aviation operations?