A project's Cost Performance Index (CPI) is 0.85. What does this mean?
-
A
The project is getting $1.18 of value for every $1 spent
-
B
The project is only getting $0.85 of value for every $1 spent
-
C
The project is 85% complete
-
D
The project is 15% ahead of schedule