CAM Cost Control and Budgeting 2 — Questions and Answers
Question 1: A control account has a BAC of $500,000, an EV of $200,000, and an AC of $250,000. What is the Cost Performance Index (CPI)?
- 0.80 (Correct answer)
- 1.25
- 0.40
- 0.50
Correct answer: 0.80
CPI = EV / AC = $200,000 / $250,000 = 0.80, meaning the account earns $0.80 of value per dollar spent.
Question 2: In earned value management, what does the Cost Variance (CV) measure?
- The difference between earned value and actual cost (Correct answer)
- The difference between planned value and actual cost
- The difference between BAC and EAC
- The difference between earned value and planned value
Correct answer: The difference between earned value and actual cost
CV = EV − AC, showing whether work performed cost more or less than budgeted.
Question 3: A Control Account Manager discovers actual costs charged to the wrong control account. What is the appropriate corrective action?
- Process a documented cost transfer to move the charges to the correct account (Correct answer)
- Adjust the budget in the receiving account to absorb the charges
- Use management reserve to offset the misbooked costs
- Leave the charges in place and note the variance in the next report
Correct answer: Process a documented cost transfer to move the charges to the correct account
Misbooked costs must be corrected through a documented, traceable cost transfer, not budget changes or reserves.
Question 4: Which budget element is held by the program manager for unknown-unknowns and is NOT part of the Performance Measurement Baseline?
- Management reserve (Correct answer)
- Undistributed budget
- Contingency in the control account
- Summary level planning packages
Correct answer: Management reserve
Management reserve sits outside the PMB and is controlled by the program manager for unforeseen in-scope work.
Question 5: A control account shows CPI = 0.90 and SPI = 1.05. How should the CAM interpret this status?
- Work is ahead of schedule but over cost (Correct answer)
- Work is behind schedule and over cost
- Work is ahead of schedule and under cost
- Work is behind schedule but under cost
Correct answer: Work is ahead of schedule but over cost
SPI above 1.0 indicates ahead of schedule, while CPI below 1.0 indicates cost overrun.
Question 6: What is the formula for Estimate at Completion (EAC) when current cost performance is expected to continue?
- EAC = BAC / CPI (Correct answer)
- EAC = AC + BAC
- EAC = BAC − CV
- EAC = AC + (BAC − PV)
Correct answer: EAC = BAC / CPI
Dividing BAC by CPI projects total cost assuming the current cost efficiency continues to completion.
Question 7: During an Integrated Baseline Review (IBR), what is the CAM primarily expected to demonstrate?
- Understanding of the scope, schedule, budget, and risks in their control account baseline (Correct answer)
- Ability to negotiate additional management reserve
- Detailed knowledge of the customer's funding profile
- Authority to change the contract statement of work
Correct answer: Understanding of the scope, schedule, budget, and risks in their control account baseline
The IBR verifies that CAMs own and understand their baseline, including scope, resources, schedule, and risk.
A control account has a BAC of $500,000, an EV of $200,000, and an AC of $250,000.
What is the Cost Performance Index (CPI)?