Professional Standards & Ethics Flashcards
7 cards from real CAM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Professional Standards & Ethics flashcards as text
A Control Account Manager discovers that reported earned value data was manipulated to hide a schedule slip. What is the most appropriate first action?
Answer: Report the discrepancy through the proper internal channels
Ethical standards require promptly reporting data integrity issues through established organizational channels.
Under EVMS guidelines, why is it unethical for a CAM to front-load a budget baseline?
Answer: It misrepresents true performance and distorts variance analysis
Front-loading inflates early performance metrics and misleads stakeholders about actual project health.
A vendor offers a CAM tickets to a sporting event during an active source selection involving that vendor. The CAM should:
Answer: Decline the gift and disclose the offer per organizational policy
Gifts during active procurements create conflicts of interest and must be declined and disclosed.
Which practice best demonstrates a CAM's ethical duty of accurate status reporting?
Answer: Reporting variances objectively even when they reflect poorly on the CAM's own control account
Objective, timely reporting of both favorable and unfavorable variances is a core ethical obligation.
A CAM is pressured by a program manager to shift charges from an overrunning control account to one with remaining budget. This practice is known as:
Answer: Mischarging, which is unethical and potentially illegal
Deliberately charging costs to the wrong account is mischarging and can constitute fraud on government contracts.
What should a CAM do if asked to certify an Estimate at Completion (EAC) they believe is unrealistically optimistic?
Answer: Document their independent analysis and refuse to certify a figure they cannot support
A CAM must only certify estimates they can substantiate with documented analysis.
Which of the following is a key element of maintaining data integrity in earned value management?
Answer: Ensuring performance is claimed only per pre-defined earning rules
Claiming performance strictly by established earning rules prevents subjective or inflated progress claims.