  1. Which FAR-level policy document establishes earned value management requirements for major acquisitions across all federal civilian agencies?

    Answer: OMB Circular A-11 (Capital Programming Guide)

    OMB Circular A-11 and its Capital Programming Guide require EVMS on major federal capital acquisitions government-wide.

  2. A CAM assigns Level of Effort (LOE) as the earned value technique for discrete design work to avoid showing schedule variance. Why is this a compliance violation?

    Answer: LOE automatically earns value with passing time, masking true performance on measurable work

    LOE earns value simply by time passing, so applying it to discrete measurable work hides real schedule performance.

  3. Under EVMS guidelines, variance analysis thresholds are established primarily to:

    Answer: Focus management attention on significant deviations requiring explanation and corrective action

    Thresholds trigger formal variance analysis so management effort concentrates on the most significant problems.

  4. Which statement about Undistributed Budget (UB) is compliant with EIA-748?

    Answer: UB holds budget for authorized scope not yet distributed to control accounts and should be allocated promptly

    UB is a temporary holding account for authorized but not-yet-distributed scope and budget, which must be distributed in a timely manner.

  5. During a DCMA surveillance review, a CAM cannot explain the basis of estimate for the Estimate at Completion (EAC). Which EVMS process area is most directly deficient?

    Answer: Analysis and Management Reports

    Developing and maintaining a credible, documented EAC falls under the Analysis and Management Reports guidelines.

  6. The Truthful Cost or Pricing Data statute (formerly the Truth in Negotiations Act) primarily requires contractors to:

    Answer: Submit and certify current, accurate, and complete cost or pricing data for covered contract actions

    TINA requires certified cost or pricing data that is current, accurate, and complete for negotiated actions above the threshold.

  7. Which entity audits contractor accounting systems and incurred costs supporting EVMS data on government contracts?

    Answer: Defense Contract Audit Agency (DCAA)

    DCAA audits contractor accounting systems and costs, complementing DCMA's EVMS compliance oversight.