← All CAM Flashcard Decks

Advanced Techniques & Methods Flashcards

7 cards from real CAM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Advanced Techniques & Methods flashcards as text
  1. A CAM notices a control account's cumulative CPI is 0.85 while the SPI is 1.05. What does this combination most likely indicate?

    Answer: Work is ahead of schedule but costing more than planned

    CPI below 1.0 indicates cost overrun while SPI above 1.0 indicates schedule performance ahead of plan.

  2. When using the 50/50 earned value technique on a work package, when is the remaining 50% of budget earned?

    Answer: When the work package is completed

    The 50/50 method earns half the budget when work starts and the remaining half only upon completion.

  3. Which formula calculates the To-Complete Performance Index (TCPI) based on the current Estimate at Completion (EAC)?

    Answer: (BAC − EV) ÷ (EAC − AC)

    TCPI based on EAC divides the remaining work (BAC − EV) by the remaining funds (EAC − AC).

  4. A CAM must replan remaining work in an open control account without changing the total budget or contract milestones. What is this action called?

    Answer: Internal replanning

    Internal replanning redistributes budget for future work within existing constraints without changing the contract budget base.

  5. Under EVMS guidelines, which practice is prohibited when closing out a completed work package with a cost variance?

    Answer: Transferring the remaining budget to mask the variance

    Shifting budget to hide variances (retroactive changes) violates EVMS baseline discipline.

  6. Which earned value method is most appropriate for a level-of-effort (LOE) activity like project administration support?

    Answer: Earned value equals the planned value each period

    LOE earns value equal to its planned value automatically, so it never generates schedule variance.

  7. A control account's Variance at Completion (VAC) is calculated as BAC − EAC and equals −$120,000. What does this tell the CAM?

    Answer: The account is projected to overrun its budget by $120,000

    A negative VAC means the estimate at completion exceeds the budget at completion, projecting an overrun.