CA Management Accounting 2 โ Questions and Answers
Question 1: Which costing method assigns all manufacturing costs (fixed and variable) to products?
- Variable costing
- Absorption costing (Correct answer)
- Marginal costing
- Direct costing
Correct answer: Absorption costing
Absorption costing (full costing) includes both fixed and variable manufacturing overhead in product costs, as required by GAAP for external reporting.
Question 2: A company has a contribution margin ratio of 40% and fixed costs of $200,000. What is the break-even point in sales dollars?
- $80,000
- $280,000
- $500,000 (Correct answer)
- $333,333
Correct answer: $500,000
Break-even sales = Fixed costs รท Contribution margin ratio = $200,000 รท 0.40 = $500,000.
Question 3: What does a favorable direct materials price variance indicate?
- More materials were used than standard
- Materials were purchased at a lower price than standard (Correct answer)
- Less materials were used than standard
- Production exceeded budgeted output
Correct answer: Materials were purchased at a lower price than standard
A favorable materials price variance means actual purchase price was less than the standard price per unit of material.
Question 4: In activity-based costing (ABC), what is a cost driver?
- The total overhead cost pool
- A factor that causes a change in the cost of an activity (Correct answer)
- The difference between budgeted and actual costs
- A fixed cost that cannot be traced to products
Correct answer: A factor that causes a change in the cost of an activity
A cost driver is the factor (such as machine hours or number of setups) that causes overhead costs to be incurred in an activity.
Question 5: Which budget is typically prepared first in the master budget process?
- Production budget
- Cash budget
- Sales budget (Correct answer)
- Direct labor budget
Correct answer: Sales budget
The sales budget is prepared first because all other operating budgets depend on the sales forecast.
Question 6: What is the purpose of a flexible budget?
- To set maximum spending limits for each department
- To compare actual costs to budgeted costs at the actual activity level (Correct answer)
- To eliminate fixed costs from performance analysis
- To allocate overhead based on machine hours only
Correct answer: To compare actual costs to budgeted costs at the actual activity level
A flexible budget adjusts budgeted amounts to the actual level of activity, allowing for meaningful variance analysis.
Question 7: Under variable costing, which of the following is treated as a period cost?
- Direct materials
- Direct labor
- Variable manufacturing overhead
- Fixed manufacturing overhead (Correct answer)
Correct answer: Fixed manufacturing overhead
Under variable costing, fixed manufacturing overhead is expensed in the period incurred rather than included in inventory cost.
Which costing method assigns all manufacturing costs (fixed and variable) to products?