A painting contractor on a public works project wants to subcontract 60% of the total painting work. Under California's Public Contract Code, this is:
-
A
Permitted if the awarding body is notified in writing
-
B
Generally prohibited; a contractor may not subcontract more than 50% of the original contract price
-
C
Allowed without restriction
-
D
Permitted only if all subcontractors are union members