BSIE Work Study & Methods Engineering 1 — Questions and Answers
Question 1: Which technique is used in work study to record all activities performed by an operator or machine on a single chart?
- Man-machine chart (Correct answer)
- Flow process chart
- Operation process chart
- String diagram
Correct answer: Man-machine chart
A man-machine chart records the simultaneous activities of an operator and machine on a time-scaled chart to identify idle periods.
Question 2: In time study, the rating factor is used to:
- Measure the actual time taken by a worker
- Convert observed time to normal time (Correct answer)
- Add allowances to normal time
- Calculate the standard deviation of cycle times
Correct answer: Convert observed time to normal time
The rating factor adjusts observed time to normal time by accounting for the pace of the worker relative to a standard pace.
Question 3: Which of the following is the correct formula for Standard Time?
- Normal Time + Observed Time
- Observed Time × Rating Factor + Allowances
- Normal Time × (1 + Allowance Fraction) (Correct answer)
- Observed Time / Rating Factor
Correct answer: Normal Time × (1 + Allowance Fraction)
Standard Time = Normal Time × (1 + Allowance Fraction), where Normal Time = Observed Time × Rating Factor.
Question 4: A work sampling study is best suited for:
- Measuring the exact time of short, repetitive tasks
- Estimating the percentage of time spent on various activities (Correct answer)
- Determining machine cycle times
- Calculating the number of motions in a task
Correct answer: Estimating the percentage of time spent on various activities
Work sampling uses random observations over a period to estimate the proportion of time spent on different activities without continuous observation.
Question 5: In a Methods-Time Measurement (MTM) system, which basic motion has the shortest normal time?
- Reach
- Grasp (Correct answer)
- Apply pressure
- Eye travel
Correct answer: Grasp
Grasp is generally the shortest basic motion in MTM, as it involves simply closing fingers on an object already in position.
Question 6: The purpose of a SIMO (Simultaneous Motion) chart is to:
- Plan factory layouts
- Record left-hand and right-hand motions simultaneously at a micro-motion level (Correct answer)
- Schedule production activities
- Analyze material flow in a plant
Correct answer: Record left-hand and right-hand motions simultaneously at a micro-motion level
A SIMO chart records the micro-motions of both hands simultaneously using therblig symbols to identify inefficiencies in hand motions.
Question 7: Which allowance in work study accounts for fatigue, personal needs, and unavoidable delays?
- Machine allowance
- Process allowance
- PFD allowance (Correct answer)
- Interference allowance
Correct answer: PFD allowance
PFD (Personal, Fatigue, and Delay) allowance is added to normal time to account for worker fatigue, personal time, and unavoidable delays.
Which technique is used in work study to record all activities performed by an operator or machine on a single chart?