Bachelor of Science in Engineering Management: Project Management Fundamentals Flashcards
7 cards from real BSE practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Bachelor of Science in Engineering Management: Project Management Fundamentals flashcards as text
Which project management process group is responsible for defining and authorizing a project or phase?
Answer: Initiating
The Initiating process group formally authorizes the project and defines its initial scope and resources.
A project manager notices that the Earned Value (EV) is $50,000 and the Actual Cost (AC) is $65,000. What does this indicate?
Answer: The project is over budget
A negative cost variance (EV - AC = -$15,000) means the project has spent more than the budgeted value of work completed.
What is the primary purpose of a project charter?
Answer: To formally authorize the project and grant the PM authority
The project charter formally authorizes the project and grants the project manager the authority to apply organizational resources.
In the context of the Critical Path Method (CPM), what is 'float' (also called slack)?
Answer: The amount of time an activity can be delayed without delaying the project end date
Float or slack is the amount of time a non-critical activity can be delayed without affecting the project's overall completion date.
Which conflict resolution technique involves finding a solution that satisfies all parties to some degree?
Answer: Compromising
Compromising seeks a solution where each party gives something up, resulting in a mutually acceptable outcome.
A project's Planned Value (PV) is $80,000 and Earned Value (EV) is $60,000. What is the Schedule Variance (SV)?
Answer: -$20,000
Schedule Variance = EV - PV = $60,000 - $80,000 = -$20,000, indicating the project is behind schedule.
Which tool is most useful for identifying the root cause of a project quality problem?
Answer: Fishbone (Ishikawa) diagram
The fishbone (Ishikawa) diagram visually maps potential causes of a problem to identify its root cause.