In risk management, what is the Risk Priority Number (RPN) calculated as?
Select your answer
A
Severity × Occurrence × Detection
B
Probability × Impact × Cost
C
Likelihood × Exposure × Vulnerability
D
Severity × Cost × Frequency
Hint