What does 'commissioning' of a new commercial building HVAC system involve?
-
A
Verifying that all systems are installed and operating according to design intent
-
B
Obtaining a certificate of occupancy from the local building department
-
C
Performing the initial startup of all mechanical equipment
-
D
Training building operators on equipment maintenance procedures