Question 1: When installing an underground gas service line, what is the minimum depth requirement for burial in BGE territory?
- 12 inches
- 18 inches
- 24 inches (Correct answer)
- 36 inches
Correct answer: 24 inches
Underground gas service lines must be buried at a minimum depth of 24 inches to protect against damage from surface activities.
Question 2: Which type of pipe joint is NOT acceptable for use in natural gas distribution systems?
- Butt-welded joints
- Threaded compression fittings
- Soldered or brazed joints (Correct answer)
- Mechanical couplings listed for gas service
Correct answer: Soldered or brazed joints
Soldered or brazed joints are not acceptable for gas piping because they lack sufficient strength and leak resistance for gas distribution pressures.
Question 3: When installing a gas meter at a residential property, what clearance must be maintained from an electrical meter?
- 1 foot
- 2 feet
- 3 feet (Correct answer)
- 5 feet
Correct answer: 3 feet
Gas meters must be installed at least 3 feet from electrical meters to reduce ignition risk in the event of a gas leak.
Question 4: What is the correct procedure when installing a new gas appliance connector?
- Reuse the existing connector if it appears undamaged
- Always install a new listed connector and never reuse old connectors (Correct answer)
- Test the old connector with soap solution before reusing
- Reuse connectors less than 5 years old
Correct answer: Always install a new listed connector and never reuse old connectors
Gas appliance connectors must always be replaced with new listed connectors during appliance installation; reusing old connectors is prohibited.
Question 5: Which material is approved for use as above-ground gas piping inside a residential structure?
- PVC pipe
- Polyethylene (PE) pipe
- CSST (Corrugated Stainless Steel Tubing) (Correct answer)
- PEX tubing
Correct answer: CSST (Corrugated Stainless Steel Tubing)
CSST is an approved material for above-ground interior gas piping and is flexible enough for use in residential installations.
Question 6: When backfilling a trench containing a new gas service line, what must be done first?
- Install warning tape 12 inches above the pipe
- Compact the native soil directly around the pipe
- Pressure test and inspect the line before backfilling (Correct answer)
- Pour concrete encasement around the pipe
Correct answer: Pressure test and inspect the line before backfilling
A pressure test and inspection must be completed and passed before any trench containing gas piping is backfilled.
Question 7: What is the purpose of installing a drip leg (sediment trap) on a gas appliance supply line?
- To regulate gas pressure to the appliance
- To collect moisture and debris before they enter the appliance (Correct answer)
- To act as an emergency shutoff valve
- To measure gas flow rate to the appliance
Correct answer: To collect moisture and debris before they enter the appliance
A drip leg collects condensation and pipe debris before they can enter and damage appliance controls or burners.
When installing an underground gas service line, what is the minimum depth requirement for burial in BGE territory?