Activity-based costing (ABC) differs from traditional costing primarily because ABC:
-
A
Uses a single overhead rate based on direct labor hours
-
B
Assigns overhead using multiple cost drivers linked to specific activities
-
C
Excludes fixed overhead from product costs entirely
-
D
Calculates overhead based on machine hours only