BEC Cost Accounting and Management Accounting 2 — Questions and Answers
Question 1: Which type of budget is adjusted to reflect the actual level of activity achieved during a period?
- Static budget
- Master budget
- Cash budget
- Flexible budget (Correct answer)
Correct answer: Flexible budget
A flexible budget is adjusted to reflect different levels of activity, making it useful for performance evaluation at the actual output level achieved.
Question 2: The standard cost for direct materials is $5.00 per unit and the actual cost was $5.50 per unit. This results in a:
- Favorable price variance
- Unfavorable price variance (Correct answer)
- Favorable quantity variance
- Unfavorable efficiency variance
Correct answer: Unfavorable price variance
Since the actual cost ($5.50) exceeds the standard cost ($5.00) per unit, there is an unfavorable direct materials price variance.
Question 3: A favorable direct labor efficiency variance indicates that:
- Actual hours worked exceeded standard hours allowed
- Actual wage rate was lower than the standard wage rate
- Actual hours worked were less than standard hours allowed (Correct answer)
- Actual units produced exceeded budgeted units
Correct answer: Actual hours worked were less than standard hours allowed
A favorable direct labor efficiency variance means actual hours worked were less than the standard hours allowed for actual production, indicating efficient use of labor.
Question 4: Which component of the master budget is typically prepared first?
- Production budget
- Cash budget
- Sales budget (Correct answer)
- Purchases budget
Correct answer: Sales budget
The sales budget is prepared first because all other operating budgets (production, purchases, labor, overhead) depend on projected sales volume.
Question 5: The overhead spending variance measures the difference between:
- Actual overhead and flexible budget overhead (Correct answer)
- Flexible budget overhead and applied overhead
- Actual overhead and static budget overhead
- Applied overhead and budgeted overhead at standard hours
Correct answer: Actual overhead and flexible budget overhead
The overhead spending variance is the difference between actual overhead incurred and the flexible budget allowance for overhead at the actual activity level.
Question 6: A company's direct labor standard is 2 hours per unit at $15/hour. Actual production was 12,000 units; actual hours were 25,000 at $14/hour. What is the direct labor rate variance?
- $25,000 favorable (Correct answer)
- $25,000 unfavorable
- $30,000 favorable
- $30,000 unfavorable
Correct answer: $25,000 favorable
Labor rate variance = (Standard rate - Actual rate) × Actual hours = ($15 - $14) × 25,000 = $25,000 favorable.
Question 7: Zero-based budgeting (ZBB) requires managers to:
- Adjust the prior year's budget by an inflation factor
- Justify all budget expenditures from scratch each period (Correct answer)
- Base budgets on a fixed percentage of forecasted sales
- Carry forward unused budget amounts to the following period
Correct answer: Justify all budget expenditures from scratch each period
Zero-based budgeting requires managers to justify every budget item from zero each period, eliminating the assumption that prior budgets are automatically justified.
Which type of budget is adjusted to reflect the actual level of activity achieved during a period?