BCM Bachelor of Construction Management MCQ 2 โ Questions and Answers
Question 1: Which contract delivery method gives the owner the most control over design decisions throughout the project?
- Design-Build
- Construction Manager at Risk
- Design-Bid-Build (Correct answer)
- Integrated Project Delivery
Correct answer: Design-Bid-Build
Design-Bid-Build separates design and construction phases, giving the owner direct control over the designer and full design approval before bidding.
Question 2: In a critical path method (CPM) schedule, what does 'float' represent?
- The total project duration
- The amount of time an activity can be delayed without delaying project completion (Correct answer)
- The lag between two successive activities
- The buffer added to account for weather delays
Correct answer: The amount of time an activity can be delayed without delaying project completion
Float (or slack) is the amount of time a non-critical activity can slip without affecting the overall project end date.
Question 3: A construction manager notices that actual costs are running 15% above the budgeted cost for work performed. What does this indicate?
- Schedule variance is positive
- Cost Performance Index (CPI) is greater than 1.0
- The project has a cost overrun (Correct answer)
- Earned value exceeds planned value
Correct answer: The project has a cost overrun
When actual costs exceed budgeted costs for work performed, the project is experiencing a cost overrun, reflected as a negative cost variance.
Question 4: What is the primary purpose of a Request for Information (RFI) in construction?
- To solicit bids from subcontractors
- To formally request clarification on contract documents (Correct answer)
- To notify the owner of a schedule delay
- To request additional payment for changed work
Correct answer: To formally request clarification on contract documents
An RFI is a formal communication tool used by contractors to request clarification or additional information about contract drawings and specifications.
Question 5: Which OSHA standard specifically governs construction industry safety in the United States?
- 29 CFR Part 1910
- 29 CFR Part 1926 (Correct answer)
- 29 CFR Part 1904
- 29 CFR Part 1960
Correct answer: 29 CFR Part 1926
29 CFR Part 1926 is OSHA's construction industry safety and health standards, covering all aspects of construction work.
Question 6: A project's Schedule Performance Index (SPI) is 0.85. What does this indicate?
- The project is 15% under budget
- The project is ahead of schedule
- The project is progressing at 85% of the planned rate (Correct answer)
- The project has completed 85% of total work
Correct answer: The project is progressing at 85% of the planned rate
An SPI below 1.0 means the project is behind schedule โ only 85 cents of planned work is being accomplished for every dollar of scheduled work.
Question 7: Which soil classification system is most commonly used in US construction and geotechnical engineering?
- Casagrande Classification System
- Unified Soil Classification System (USCS) (Correct answer)
- AASHTO Soil Classification System
- MIT Classification System
Correct answer: Unified Soil Classification System (USCS)
The Unified Soil Classification System (USCS) is the most widely used system in US construction and geotechnical engineering practice.
Which contract delivery method gives the owner the most control over design decisions throughout the project?