BCM Bachelor of Construction Management 2 — Questions and Answers
Question 1: Which contract delivery method gives the owner the most control over design details?
- Design-Build
- Construction Manager at Risk
- Design-Bid-Build (Correct answer)
- Integrated Project Delivery
Correct answer: Design-Bid-Build
Design-Bid-Build separates design and construction phases, letting the owner fully approve design documents before soliciting construction bids.
Question 2: In construction scheduling, what does 'float' (or slack) represent?
- Extra budget held in reserve
- The amount of time an activity can be delayed without delaying the project (Correct answer)
- Overtime hours available to workers
- Material surplus kept on site
Correct answer: The amount of time an activity can be delayed without delaying the project
Float is the amount of time a non-critical activity can be delayed without pushing back the project's overall completion date.
Question 3: What is the primary purpose of a Geotechnical Investigation before construction begins?
- Determine zoning restrictions
- Assess soil conditions and bearing capacity (Correct answer)
- Survey property boundaries
- Estimate material quantities
Correct answer: Assess soil conditions and bearing capacity
Geotechnical investigations analyze subsurface soil and rock conditions to determine the ground's ability to support proposed structures.
Question 4: A contractor submits a claim for additional compensation due to unforeseen site conditions. Under which clause is this typically addressed?
- Liquidated Damages clause
- Differing Site Conditions clause (Correct answer)
- Force Majeure clause
- Indemnification clause
Correct answer: Differing Site Conditions clause
The Differing Site Conditions clause (also called Changed Conditions) allocates risk when actual site conditions differ materially from what the contract documents indicated.
Question 5: Which OSHA standard specifically governs safety requirements for construction industry workers in the US?
- 29 CFR Part 1910
- 29 CFR Part 1926 (Correct answer)
- 49 CFR Part 172
- 40 CFR Part 261
Correct answer: 29 CFR Part 1926
29 CFR Part 1926 is OSHA's Construction Industry Standards, covering fall protection, scaffolding, excavation, and other construction hazards.
Question 6: What is 'Value Engineering' in construction management?
- Increasing project scope to add value for the owner
- A systematic method to improve the value of goods or services by examining function (Correct answer)
- Calculating the depreciation of construction equipment
- Bidding below cost to win a contract
Correct answer: A systematic method to improve the value of goods or services by examining function
Value Engineering analyzes project functions to achieve required performance at the lowest life-cycle cost without sacrificing quality, reliability, or safety.
Question 7: In a Critical Path Method (CPM) schedule, which activities have zero float?
- Activities on the critical path (Correct answer)
- Activities with the most resources
- The first and last activities only
- Activities assigned to subcontractors
Correct answer: Activities on the critical path
Critical path activities have zero float, meaning any delay to them directly extends the project's overall completion date.
Which contract delivery method gives the owner the most control over design details?